Products and services using Tidal turbines are generally available around 2018
Grader A: partial
Grader B: partial
agrees with A, without seeing its verdict
Audit: confirmed
in the fixed audit sample (D11)
Published: partial
Grader A: partial
MeyGen began commercial operation in April 2018 with 6 MW and sells power to the GB grid, but it is the largest tidal-stream project in the world and expansion to 28 MW is only planned for 2027. Real but limited availability, as the poster's own 'small scale' note already described.
Test: D37 Horizons: tidal-stream electricity or turbines sold to ordinary customers outside pilots by 2020; a few small arrays count as limited availability.
Grader B: partial
Tidal turbines produce grid power only in small arrays: MeyGen's 6 MW demonstration array entered operations in April 2018; global tidal-stream capacity stays tens of MW. Real but limited.
Test: Tidal-turbine power or units could be bought outside pilots by 2020; partial if limited/demonstration.